Rooftop Waterproofing

Safe construction, happy future Jese Architecture 010-6314-9810
 

Urethane construction construction

1. Floor work

Use a hand grinder to grind and clean the existing contaminated surface or existing waterproof layer.


Rooftop waterproofing work

2. Subway work

Use the

roller to sufficiently penetrate the floor.


Rooftop waterproofing work

3. Silicone Work

Fills cracks and cracks at the corners of buildings with silicone or partner.


Rooftop waterproofing work

4. Medium operation

Pour

neutralizer on the floor and spread it evenly using a rolling pin. The thickness should be about 2~3mm.


Rooftop waterproofing work

5. Top coat work

Apply with roller the next day after mid-treatment.


Rooftop waterproofing work

6. Completion

This is the completed rooftop.


Rooftop waterproofing work

Rooftop waterproofing work
Green Waterproof Master Undercoat
Rooftop waterproofing work
Green Waterproof Master Jungdo
Rooftop waterproofing work
Green Waterproof Master Topcoat